Preferred Freezer

Location: 400 Hudson, San Leandro
General Contractor: Victory Unlimited Construction, LLC
Subcontractors: Joseph L. Easley Construction, Gesick Concrete, Interstate Concrete Pumping
Concrete Supplier: Central Concrete Supply Co., Inc.

Project Highlights

Preferred Freezer Services began construction on October 2013. The state-of-the art, temperature-controlled warehouse at the 15-acre former Hudson Lumber site will provide cold storage of truits, nuts, meats and other food products for export or import. Administrativ offices as well as shipping and receiving facilities also are incorporated into the 247,000 square-foot design

Central Concrete provided approximately 18,000 cu yds. of concrete. The three cold-storage freezer bays, with automated racking systems, required super flat floor tolerances.

Return to Project Listing »

 